BUILD WATCH · PERTH-WIDE SIGNAL

Bricks are a build-timing story.

High prioritySupply constrained

WA brick constraints can delay home builds

Strong demand has put pressure on WA brick supply. The State has committed up to $4 million to help restart Austral's Cardup brickworks, but the extra capacity is not an immediate fix.

Checked 8 October · review due 9 October 2026

WHY THIS CLEARS THE BAR

Broad reach, real timing consequences, strong evidence.

The score controls review priority. It is not a prediction of the delay on any individual home.

5/5

People affected

4/5

Time or money

4/5

Useful now

5/5

New development

5/5

Evidence

What is confirmed

  • The WA Government announced up to $4 million to support recommissioning the Cardup brickworks.
  • The facility is expected to add about 17 million Maxibricks and lift WA supply by roughly 10–15 per cent once operational.
  • The incentive target is to resume operations by March 2027; industry representatives warned the benefit will take time to reach current builds.

What is not known

  • Whether a particular builder or site is waiting for an allocation.
  • The exact delay or cost impact for an individual contract.
  • Whether the restart timetable or first-year production target will be met.

IF YOU ARE BUILDING

Ask for the site-specific position.

A statewide shortage does not prove that your project is delayed. The builder should be able to explain the current sequence and any proposed variation.

  1. 01

    Is my site affected by a brick allocation or a bricklayer shortage?

  2. 02

    What is the current expected delivery and bricklaying date?

  3. 03

    Does any proposed material change affect price, appearance, approvals or warranty?

  4. 04

    Can the revised sequence and any cost variation be confirmed in writing?