BUILD WATCH · PERTH-WIDE SIGNAL
Bricks are a build-timing story.
WA brick constraints can delay home builds
Strong demand has put pressure on WA brick supply. The State has committed up to $4 million to help restart Austral's Cardup brickworks, but the extra capacity is not an immediate fix.
Checked 8 October · review due 9 October 2026
WHY THIS CLEARS THE BAR
Broad reach, real timing consequences, strong evidence.
The score controls review priority. It is not a prediction of the delay on any individual home.
5/5
People affected
4/5
Time or money
4/5
Useful now
5/5
New development
5/5
Evidence
What is confirmed
- The WA Government announced up to $4 million to support recommissioning the Cardup brickworks.
- The facility is expected to add about 17 million Maxibricks and lift WA supply by roughly 10–15 per cent once operational.
- The incentive target is to resume operations by March 2027; industry representatives warned the benefit will take time to reach current builds.
What is not known
- Whether a particular builder or site is waiting for an allocation.
- The exact delay or cost impact for an individual contract.
- Whether the restart timetable or first-year production target will be met.
IF YOU ARE BUILDING
Ask for the site-specific position.
A statewide shortage does not prove that your project is delayed. The builder should be able to explain the current sequence and any proposed variation.
- 01
Is my site affected by a brick allocation or a bricklayer shortage?
- 02
What is the current expected delivery and bricklaying date?
- 03
Does any proposed material change affect price, appearance, approvals or warranty?
- 04
Can the revised sequence and any cost variation be confirmed in writing?